Joint Oireachtas Committee on Health
Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board
9:30 am
Seán Kyne (Fine Gael) | Oireachtas source
I take up Deputy Kenny's point. Some 94% of the building is complete. That is positive. However, the witnesses are saying that the issues relate to what are more than snags and are important issues relating to completing the sign-off of the individual rooms. Were those issues that could not have been seen in the oversight as the building and the first rooms were going along? Could they not have been told to hold on a minute, something different was needed or something was not compliant, and needed to be sorted out before the rooms were completed? Is that not the detailed hands-on work that is needed on a project like this?