Mr. Phelim Devine:
No, a process was entered into with the ER, the independent person who, under the contract, determines whether the programme is compliant or not. She entered into a long process with BAM between September or October and early 2024. On 2 April, she determined that the baseline programme was not compliant and requested a revised programme. She then again requested a revised programme in June. BAM wrote back to say it would issue one in July. It issued a programme in July and the ER has since gone through that programme and any progress updates since then.