Oireachtas Joint and Select Committees

Wednesday, 15 November 2023

Joint Oireachtas Committee on Climate Action

Future Licences and Contracts to Connect Data Centres to the Gas Network: Discussion

Ms Marie Donnelly:

I might be incorrect on some of these. I understand the new Celtic interconnector is a 700 MW one, the east-west interconnector is 500 MW and the Greenlink coming on stream is approximately 500 MW.

It is good. We could probably have as much again because it is a safety valve and very useful from that point of view.