Roll-out and Delivery of Broadband in Rural Areas: Discussion
Mr. Peter Hendrick:
Mr. Malone may correct me if I am wrong. Typically, it can take anything up to 30 days to get specific licences approved but, in general, the programme and the engagement with local authorities have been quite good. I would not say there has been an issue with the local authorities around connections. There is a time within which we have to submit the licence and a time within which the licence comes back and is approved and the contractor commences work and mobilises a team.