Update on New National Children’s Hospital: National Paediatric Hospital Development Board

Mr. David Gunning:

If we just take the time from the contractual completion date of November 2022 up to 7 May, the period BAM is talking about, this is 405 working days. If we count the number of days, the total is 405. Yet BAM is actually claiming for 2,376 days just on these extensions of time, EOTs, alone. It is, therefore, claiming nearly six times for each day, with duplicate claims, overlapping claims, etc. Someone mentioned mechanical and electrical, M&E, claims earlier and several of these are all layered on top of each other as well.