Oireachtas Joint and Select Committees
Thursday, 30 March 2023
Public Accounts Committee
Business of Committee
9:30 am
Colm Burke (Cork North Central, Fine Gael) | Oireachtas source
One of the problems with this contract is that there are a lot items that are disputed or are going to be disputed. The project will be completed, but the dispute regarding outstanding, additional works where the contractor is looking for payment could go on for at least 18 months, if not two to three years, after the project is fully finished. That would be one of the problems regarding getting a final figure.