Mr. Coil?n O'Reilly:

It could take anything from four to five months up to nine to ten months. It can be quite long, depending on the developer, the engagement, the costing and the level of information provided. We obviously have our own quantity surveyors to do an assessment of the costing and there can be an element of back-and-forth with regard to that. Therefore, it depends. There is no fixed average; it depends on the project.