Mr. T.J. Malone:
I thought for a minute that the Deputy was going to forget to do so. There are small numbers in County Louth. There is the figure of 8,249 within Louth of premises within the intervention area.
We have passed 3,231 at the moment, so they are available for connection. There are 3,402 built, so there are about 170 to come into the mix shortly. By the end of this year, we will have 4,189, so almost 50% of Louth will be fully built.
All the surveys will be completed by 2023, while 72% of builds will be commenced by 2023 with 100% commenced by the end of 2024. The build-complete for 2024 is 66%. I will come back to the Deputy on the 2023 number on that. I do not have it at the moment.