Joint Oireachtas Committee on Transport, Tourism and Sport
National Broadband Plan Update: National Broadband Ireland
Mr. Peter Hendrick:
To put the 63,000 into perspective, as of tomorrow we will also be notifying industry of another nearly 4,000 premises, so then it will be 67,000. The retailers will know that those houses will be live in two weeks' time. They can place orders and they go into the provisioning cycle. Pretty quickly, the 74,000 Mr. Malone has spoken of will go through that same process. Every two weeks we release premises. Every two weeks we have a new drop of premises going from built to passed.