Joint Oireachtas Committee on Transport, Tourism and Sport

National Broadband Plan Update: National Broadband Ireland

Mr. T.J. Malone:

Basically, the start of it is the Eir make-ready work once we get on the ground. We give the file and design to Eir to start the build work at that stage. It can take probably six months for Eir to get that make-ready work finished. We will start some of our own work in parallel to that.