Dr. Ciaran Byrne:

The reason it takes 12 weeks is one of the last parts of a home upgrade is the reclipping of the electrical wires, which takes a period and then the home is fully complete. We have looked at bringing that payment cycle much closer so the contractors do not have a cash flow problem and so they can deliver more homes. We are engaged on that issue.