Oireachtas Joint and Select Committees

Thursday, 10 February 2022

Public Accounts Committee

2020 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 29 - Environment, Climate and Communications
National Broadband Plan Expenditure and Related Matters

9:30 am

Photo of Brian StanleyBrian Stanley (Laois-Offaly, Sinn Fein) | Oireachtas source

It would be €5,000 if everybody took it up and we can do the sums from there. This is relating to the overall cost of the project, which is €2.9 billion. We can divide that by the number of premises to be served, and we can assume 40% of premises will take it up. I hope more premises take it up. If 50% of premises take it up, the cost is €10,000 per connection. Is that excessive?