2020 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 29 - Environment, Climate and Communications
National Broadband Plan Expenditure and Related Matters

9:30 am

Mr. T.J. Malone:

We have not completed all of the service or design in a low level, as of yet. From our high-level designs and from the work we have done to date, we would see for building the network itself - just the network - somewhere between 90,000 km and 96,000 km of fibre to be deployed over the period. Over the 25 year-period, we would be estimating somewhere in the region of 145,000 km, including the connections.