I will take the Deputy through the survey, the build-commencing and build-complete dates, by year. Some 42% of premises in the county have been surveyed. By the end of 2022, almost 55% will have been surveyed. From a build-commenced point of view, 24% of the entire premises in Clare, in the intervention area, are under construction as of the end of 2021. If I roll that forward to 2023, 42% will be under construction. By 2024, 66% will be under construction and by 2025, 100% will be under construction. By the end of 2022, 5,280 premises or the equivalent of almost 25% of premises in the county will be completed in the build. By 2024, 42% will be completed. By 2025, 64% will be completed and the balance will be completed in 2026.