National Transport Authority: Financial Statements 2020
9:30 am
Mr. Hugh Creegan:
The expenditure over the past four years on the MetroLink project was €88 million. Most of that expenditure has been on design and planning work and a substantial part was on investigative work, be that ecology surveys, ground investigation surveys or similar exercises such as traffic surveys and so on. It is an extremely large project and that level of expenditure is what we would expect for a project of this magnitude to develop it to a sufficient level in order that it can confidently be brought into construction.