National Broadband Plan: Discussion

Mr. Patrick Neary:

In Roscommon there are 4,609 premises, in total, which are scheduled for completion before the end of the year. As regards activity across all of Roscommon, 42% of the premises have undergone a survey at this point. Some 7,700 premises are in pre-build and build work. There is substantial activity happening across Roscommon in total. While I have the opportunity I will clarify the numbers I gave earlier and the reason there is a discrepancy. Mr. Ó hÓbáin referred to 113,000 in build. That was at the date stamp of the end of September. The number I have of 111,000 is because up to a number of days ago 2,000 have moved into complete. That is the only difference. They are the same figures. I will refer back to the committee on the list of marts.