Mr. Mark Griffin:

They have been awarded. I am not sure whether they have been fully awarded. We have moved to a situation where NBI will do the connections again, but the subcontracts will be carried out by a range of contractors, as I understand it. They are being appointed by the Department of Education. At this stage, of the 379 schools, 141 have been connected. There will be a cumulative figure of 200 by the end of this year. The full 679 schools will be connected by the end of 2022. We have brought that forward.