Mr. Fergal Mulligan:

No. The existing milestone is already in the contract that we signed in 2019. What the company needs to do is come to us and explain why it cannot achieve it. As Mr. Griffin said, we kick this up and down to make sure we understand whether something is down to Covid or caused by National Broadband Ireland itself or a subcontractor. We do all of this work to establish what it was supposed to achieve, which was the 200,000, versus what it can achieve. The contract is re-baselined based on this. This does not mean it gets a free pass because we change the numbers. It will still get hit with delayed payments based on the original contract.