Mr. Mark Griffin:

No. I mentioned that as an example of the challenges that the company face but there were supply chain and logistic delays both nationally and internationally. One of the contractors that had intended coming over from the UK to start work on the project postponed establishing its Irish operation; recruitment and the onboarding of key staff was delayed; as was travel and availability of accommodation for contractors across islands, and access to islands in some schools for the installation of BCPs. So there was a whole swathe of problems, Deputy, that led to a situation.