2020 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 29 - Environment, Climate and Communications
Chapter 9 - Remediation of Landfill Sites

9:30 am

Mr. Fergal Mulligan:

It has been and that is what we approved in our review of the remedial plan with NBI in March 2021. As of today, NBI is six months behind in its network roll-out. We are trying to establish now whether the company can catch up on that six-month delay. The company is not paying delay payments now because the other contract does not start until February 2022.