National Paediatric Hospital Development Board: 2019 Financial Statement (Resumed)

9:30 am

Mr. Phelim Devine:

Yes, it is finished for Connolly Hospital Blanchardstown. We have some contracts in place for Tallaght University Hospital. We are putting the rest of them in place this minute to equip that facility out by between September and November this year. We are in procurement on the new children's hospital job for the group 2 equipment, which is actually the equipment that gets built into the building. That is currently in procurement and the balance of that will be done by the end of the year. The group 3 and 4 equipment, which is what we call plug and play equipment, will not be procured until next year and 2023 ahead of going in in 2024.