National Paediatric Hospital Development Board: 2019 Financial Statement (Resumed)

9:30 am

Mr. Phelim Devine:

The contract sets out that the seven month period is recoverable. The contractor recovered time for that period. The original contract substantial completion date was August 2022. That has been extended to October 2022 for the shutdown period. The other period when the contractor was not back to site is not recoverable nor possibly are some of the impacts that are ongoing. That is being disputed by the contractor and is one of the claims referred to earlier by Mr. Gunning.