Ms Hilary Murphy-Fagan:
I thank the Deputy for her question. The cost of the programme in 2016 was €54 million, including VAT. The figure of €115 million also includes VAT. When the programme and business case were developed in 2015 and approved by the Government in 2016, it was considered that a delay in the programme was possible and, therefore, that the cost of the programme could be €72 million, including VAT. That delay has now-----