National Paediatric Hospital Development Board: 2019 Financial Statement
1:00 pm
Brian Stanley (Laois-Offaly, Sinn Fein) | Oireachtas source
On the completion timeline, my calculation is that the board is looking at spring 2024. Does Mr. Gunning agree with that? He said the contractors are now ten months behind and there is also a nine-month phase to crank up operations and test operations. Is that correct, when we add that 19 months to the revised time of August 2022?