National Children's Hospital

Mr. David Gunning:

I believe we summarised it very roughly in the report. Before Covid, in March of this year, the project was approximately six months behind schedule. Then there were further delays, including the seven weeks of the Covid period and a further seven weeks after the date for the reopening of construction sites, 18 May, when the contractor failed to return to work, adding further to the delay. Those two periods, added to the accumulated delay in March, would give a clear indication as to where the project was and is currently in terms of the accumulated delay.