National Broadband Plan Roll-out: Discussion
Ruairí Ó Murchú (Louth, Sinn Fein) | Oireachtas source
I thank the witnesses for participating. The crux of the matter has already been addressed in the many questions that have been asked.
Some 132,000 premises have been surveyed, there have been designs in respect of 92,000 premises and network is currently being built for 19,500 premises. What are the possible timeframes from survey and design to build? In terms of the build phase, it was mentioned that NBI was considering accelerating the timeframe. When will that happen? Although information on timeframes for areas is lacking, I welcome that there will be a figure in four to six weeks' time.