National Broadband Plan Roll-out: Discussion
Mr. T.J. Malone:
They have already been surveyed so they are going through the design process. The first 1,300 of these premises are under construction. When we go into construction it can take between six and nine months before they are ready for connection. The first 1,300 of them are now under construction and that started a couple of months ago. They should be ready for connection in June next year.