Oireachtas Joint and Select Committees
Wednesday, 11 November 2020
Public Accounts Committee
2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
4:30 pm
Matt Carthy (Cavan-Monaghan, Sinn Fein) | Oireachtas source
We have determined that a contract that was envisaged to amount to about €12 million over the course of four years actually amounted to closer to €50 million over that period. More recently, in October 2018, a new tender was appreciated. The provisions the OPW put in place, that is, the guidelines for contracting companies, meant there was, in effect, only one qualifying tender application or expression of interest.
No comments