Seán Fleming (Laois, Fianna Fail) | Oireachtas source
Mr. Gunning mentioned that additional procurement will be needed for equipment for the project. Can everything for the period from 1 January 2019 to the hand-over of the hospital be completed for €176 million to give the figure of €1.433 billion? We are not talking about inflation. Does Mr. Gunning have an estimate of what further costs will be incurred to complete the project? Does he follow me? It am trying to get the big picture.
No comments