Update on Construction of National Children's Hospital: National Paediatric Hospital Development Board

Mr. Fred Barry:

Generally speaking, yes, that is the builder's problem. An exception would be if we did something on our side that delayed the contractor, then the cost would fall to us. The contractor bears the risk for delays arising because of resource issues or because there is so much to be done, as part of the GMP.