Mr. Fred Barry:

No. In terms of part of what we are doing in managing the costs, as the construction documentation has been issued by the design team, it has been closely vetted to ensure that the design, as it is being issued for construction, is consistent with the design as was used to negotiate the guaranteed maximum price. Of course, as design develops there are bits and pieces of changes as things move around but there have been no changes that have any significant impact on the costs.