Upgrade of the Dunkettle Interchange in Cork: Transport Infrastructure Ireland
Mr. Paul Moran:
Mr. Walsh mentioned that it was a four-year contract. The idea is that the more planning is done, the quicker one gets in and out of the site in question, and the less disruption is caused. We gave the successful contractor leeway in that. If it felt it could be done in a year, and then spent three years on construction, so be it. The idea was to ensure it was properly planned in order to get in and out of the site as quickly as possible.