My next questions are on the refurbishment of Leinster House and conservation works. We all look forward to that being completed and opened. If there is a grand opening, we will all be there. I just want to look at the costs. While I do not believe everything I read in the newspapers, no more than anyone else, the initial reports on the project in an article in The Irish Timesof May 2017 were that it would cost €8 million. The article stated:
While the final cost of the work has yet to be determined, the OPW said last December that it would be at least €8 million.
At what point were the initial costs worked out? Was that figure accurate and was the OPW accurate in saying it would be at least €8 million? Was that an estimate or what was that based on?