Mr. Conor O'Kelly:

Every part of the fit-out has to be publicly procured. It is a high-specification building. The NTMA has some fairly sophisticated mandates. To put it in context, $1 trillion went through the NTMA's settlement system and treasury system in 2018 alone. There is significant cabling infrastructure to be put in place. It is reasonable value. The budget is set and a project board is in place which includes non-executives. We have remained on budget. The Comptroller and Auditor General has been looking at the numbers very carefully.