Oireachtas Joint and Select Committees

Tuesday, 16 April 2019

Joint Oireachtas Committee on Communications, Climate Action and Environment

Microgeneration Support Scheme Bill 2017: Discussion (Resumed)

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party) | Oireachtas source

Before we move on to that, I agree that we need massive interconnection to help us when we reach that 70% penetration level. It makes massive sense for us to have flexibility, not just in the context of the line to France but also with a significant number of interconnectors to give us that capability. I would like those interconnectors to be in the ownership of EirGrid in order that the transmission system will be a public asset.

My next question may involve straying away from microgeneration slightly but it is connected. Has EirGrid carried out a needs-based analysis to show that we need large numbers of new gas-fired combined cycle gas plants in the scenario whereby we have 70% renewables penetration? Would the company see that as being essential? If we are to do interconnection and if we are achieving 70% renewables, do we need many additional gas plants?

Comments

No comments

Log in or join to post a public comment.