Oireachtas Joint and Select Committees
Thursday, 7 March 2019
Joint Oireachtas Committee on Finance, Public Expenditure and Reform, and Taoiseach
National Children's Hospital: Discussion with Department of Public Expenditure and Reform
Kieran O'Donnell (Fine Gael) | Oireachtas source
Therefore, would that not be a point that needs to be addressed? There was a weakness within that particular process because it meant whoever got appointed for phase A and phase B was getting detailed underground but preliminary design overground. That created a weakness in the procurement process.