2017 Annual Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 34 - Housing, Planning and Local Government

9:00 am

Mr. Conn Murray:

In total, there are 695 in the current plan that we have agreed with the communities for delivering. Of those, 300 are either in construction or being delivered currently, and the balance is already going through the stages with the Department. That is a ten year plan and we are already four years ahead of that. Overall they are the units we have to provide. I cannot go back over the history of it and say how many were demolished. All I know is what we are doing to work with the community to deliver homes.