Mr. Jim Breslin:

Because all of the detailed work was being priced. The development board originally had in the contract 2 November as the close-out date for the guaranteed maximum price process. It agreed with the three contractors - BAM, Mercury Engineering and Jones Engineering - that it would be extended by three months, until December, in order to complete the process.