National Paediatric Hospital Development Board: Financial Statements 2017
9:00 am
Seán Fleming (Laois, Fianna Fail) | Oireachtas source
The detailed design for phase B, which accounted 90% of the job, was not completed when the contract for the full project was awarded. It is very simple. It was open to a contractor to get on site to do phase A, which accounts for 10% of the job, knowing that it had landed the entire contract and that the board had no bargaining position because a detailed design had not been done. It essentially awarded-----