National Children’s Hospital: National Paediatric Hospital Development Board
Mr. Tom Costello:
Part of the process is that the contractor is engaged on site in doing the phase A works. At the same time the contractor works with the design team in developing the design, in this case for more than a year. Then, on the basis of the quantities that come out of the completed design, the final price is evaluated. Perhaps Mr. Pollock can go through it again to finalise or clarify that.