Oireachtas Joint and Select Committees
Thursday, 5 July 2018
Joint Oireachtas Committee on Finance, Public Expenditure and Reform, and Taoiseach
Contractual Arrangements for Public Sector Infrastructural Projects: Discussion
9:30 am
John McGuinness (Carlow-Kilkenny, Fianna Fail) | Oireachtas source
It is correct. A total of €85.3 million of a contract worth €87 million was paid. The National Development Finance Agency had oversight of the system of payment. It seems that the main contractor was paid and that money did not filter down to the other contractors. Is that the position?
No comments