Mr. Michael Kennedy:

In the briefing document provided we have not provided projections for traffic guarantee or variable operation payments as they are described. To date, we have paid €34.1 million for the Limerick tunnel and prepared future projections for what we consider to be conservative traffic growth scenarios. The future payments would amount to approximately €150 million. We provided this information by year in the briefing documents submitted to the committee. In total, we are looking at a figure of €200 million in traffic guarantee related payments under the scheme.