Mr. Gerard Cahillane:
It is done for each project we are involved in the delivery of. In some of the earlier projects, we found that the procurement process was very long. There were many complaints from the market that it was very expensive. We decided that, in the case of PPPs, we would not ask the private sector to get full planning permission and instead we would obtain planning permission for these facilities.