Oireachtas Joint and Select Committees

Thursday, 8 October 2015

Public Accounts Committee

National Paediatric Hospital Development Board Fund: Finance Statements 2013

10:00 am

Mr. John Pollock:

When we last met we had only appointed our design team in August 2014. Almost a year to the day later, on 10 August 2015, we had completed the design to a stage where we could lodge the planning application. So that went in to An Bord Pleanála, because it comes under strategic infrastructure. An Bord Pleanála then basically writes out to prescribed organisations, of which I think it has identified 19. We had to issue them with copies of the application and the planning documentation. The time period was from 10 August to last Friday, 2 October, for any members of the public to lodge observations, either in support of the project or with concerns about the project.