North-South Interconnector: EirGrid
11:30 am
Mr. Fintan Slye:
An underground line has to be a high-voltage, direct current, HVDC, line to go the length of North-South which is 140 km. With a 220 kV line, we would still be achieving only a very small proportion of the length that could go underground. Bringing it back from 400 kV to 220 kV would maybe get-----