Ms Clare McGrath:

The outline design of the proposed scheme is being finalised following on from the comments and views submitted on and since the public information days. The required statutory public exhibition was originally to take place over a six-week period. In finalising the preferred option, following the public information process, we have had regard to the input of local stakeholders, in particular, in terms of how the dams will be used and the forecasting system. It has been quite complex. We are talking about mid-2015 for completion of the public exhibition phase.