Oireachtas Joint and Select Committees

Thursday, 13 June 2013

Committee on Education and Social Protection: Select Sub-Committee on Education and Skills

Vote 27 - Education and Skills (Revised)

12:05 pm

Photo of Ruairi QuinnRuairi Quinn (Dublin South East, Labour) | Oireachtas source

On the minor works grant, the note I have states that in 2012 a total of 52 large-scale projects were substantially completed and that it is planned that 113 major school projects will be undertaken on site in 2013. The grant was last issued in November 2011. All of the management bodies were advised that a minor works grant was unlikely to be available in the coming years for the reasons I stated, namely, that all available capital was going towards new build rather than refurbishment and upgrading works. I accept the argument that early maintenance saves the capital cost of replacement down the road, but we have to make choices.