Oireachtas Joint and Select Committees

Thursday, 7 February 2013

Public Accounts Committee

2011 Annual Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 32 - Department of Transport, Tourism and Sport
Chapter 6 - Financial Commitments Under Public Private Partnerships
Chapter 26 - Collection of Motor Taxation
Financial Statements 2011 - National Roads Authority

10:40 am

Mr. Fred Barry:

We received a breakdown totalling €6 million but we did not accept all of it. Issues also arose in respect of quarries and material that should have been made available. All of the PPP construction contracts provide that if the State's standards change during the course of construction, the additional costs are picked up by the State. That arose in regard to CIE standards relating to bridges over railway crossings.

Comments

No comments

Log in or join to post a public comment.