Oireachtas Joint and Select Committees

Thursday, 6 December 2012

Public Accounts Committee

2011 Annual Report of the Comptroller and Auditor General and Appropriation Accounts
Chapter 6 - Financial Commitments under Public Private Partnerships
Chapter 16 - Central Government Funding of Local Authorities

1:50 pm

Photo of Eoghan MurphyEoghan Murphy (Dublin South East, Fine Gael) | Oireachtas source

Even as costs continued to rise? There was a jump of €20 million between 2005 and 2007, which were the two years in which value for money reports were produced. This was the case even when the Department thought the €17 million it had invested in the project was like a drop in the ocean at less than 10% of the actual costs coming up to the beginning of 2012.