Oireachtas Joint and Select Committees

Thursday, 6 December 2012

Public Accounts Committee

2011 Annual Report of the Comptroller and Auditor General and Appropriation Accounts
Chapter 6 - Financial Commitments under Public Private Partnerships
Chapter 16 - Central Government Funding of Local Authorities

11:40 am

Ms Maria McLoughlin:

Our Department is responsible for putting in place the guidelines. They require that value for money tests are conducted at different stages before the contract is entered into. Management of the projects is a responsibility of the sanctioning authority which would be the Department that put in place the project. The tests would be a matter for them and not for our Department. Our responsibility is to put in place the guidelines. It is up to the sanctioning authority to implement them.

Comments

No comments

Log in or join to post a public comment.